How To obtain Commencement Certificate for beginning the construction work in respect of cases where Building plan approval is already obtained from BDA in Karnataka?






Name of the Department BANGALORE DEVELOPMENT AUTHORITY
Name of the Service To obtain Commencement Certificate for beginning the construction work in respect of cases where Building plan approval is already obtained
Whom to approach for this service (Designated Officer)? Engineer Officer
Procedure involved to get this service Filling application for this service along with relevant documents indicated, at the office of the concerned Engineer Officer in BDA Bangalore, and obtain an acknowledgement. The submitted application will be processed and the service will be delivered to the applicant from that section.
Who are eligible to get this service 1)The sites allotted by BDA those allottes. 2) The building shall be inspected by concerned EEs/AEs as per the approved set backs by BDA.
Documents to be enclosed with the request

1 . Application on a plan paper requesting for this service

2 . Approved site plan copy

3 . Tax paid receipts

4 . Attested copy of khatha

5 . Licence from local organization

Fee/Charges to be paid to get the service No Fee.(Rs.50/sq mt penality,if building has started without commencement certificate)
Maximum number of days to wait to get this service delivered 12 Working Days
Whom to approach as a appeal (Competent Officer), if the service is not delivered in time or rejected by officer Engineer Member
Maximum number of days to wait to get the decision of the Competent Officer 15 Working Days
Whom to approach as 2nd appeal (Appellate Authority), if the decision of the Competent officer is not acceptable or not implemented? Commissioner
Maximum no. of days to wait to get the decision of Appellate Authority 15 Working Days
Other information

www.bdabangalore.org


Work Flow

Step

Description

No. of Days

Designation

1

The applicants have to submit their applications along with prescribed documents at the following offices of the concerned designated officers in concerned divisions and obtain an acknowledgement.

0.00

Engineer Officer

2

Inward of application from engineer officer for further action it has been forwarded to assistant engineer.

1.00

Engineer Officer

3

Application will be inspectioned and verified by assistant engineer and assistant executive engineer and then application will be sent to executive engineer.

2.00

Executive Engineer

4

The application will be verified by the executive engineer and forwarded to engineer officer.

2.00

Engineer Officer

5

Finally application will be verified by the engineer officer.

2.00

Engineer Officer

6

Approval by the engineer member/commissioner

2.00

commissioner

7

Issue of commencement certificate by engineer officer.

3.00

Engineer Officer

How would you rate the answer?


Excellent Good Neutral Poor Bad

Thank you for your response..


tesz.in
Hey , can you help?
Answer this question

Guide

Karnataka Voter List 2024 - Search By Name, Download

Empowering citizens to exercise their democratic rights is crucial, especially in the vibrant state of Karnataka. This concise guide offers clear steps for downloading the voter list, searc..
  Click here to get a detailed guide