How to get approval for change of land use in BMRDA limit in Karnataka?






Name of the Department BANGALORE METROPOLITAN REGIONAL DEVELOPMENT AUTHORITY
Name of the Service Approval for change of land use in BMRDA limit
Whom to approach for this service (Designated Officer)? Member Secretary, Planning Authorities
Procedure involved to get this service Concerned Planning Authority/Urban development authority has to submit the proposal duly following the requirements of Sec 14-A of Karnataka town and country planning act 1961 and guidelines issued by the govt. dated 12.10.2012.
Who are eligible to get this service Land owner or person authorized on behalf of land owner shall submit the application to concerned PA/UDA and the respective authority is to forward the proposal to BMRDA
Documents to be enclosed with the request

1 . Sale deed or partition deed

2 . Latest EC form no 15 and 16

3 . Original survey sketch showing the all-round dimensions, village map, akarband duly certified by competent authority

4 . Latest copy of records of right RTC, copy of mutation khata certificate and land acquisition details if any

5 . Site plan prepared using total station showing the dimensions of land, contours and surrounding details within 100 mts. From the edge of the property

6 . Certification from concerned revenue authority regarding PTCL 79 a b case under Karnataka land reforms act, 1964

7 . Google earth image showing land in question and surrounding developments upto 100mts. From the edge of the property

8 . Approach road details viz. Classification of road, width of road etc.

9 . Approved master plan extract showing the land in question

Fee/Charges to be paid to get the service As per the Goverment Rules
Maximum number of days to wait to get this service delivered 120 Working Days
Whom to approach as a appeal (Competent Officer), if the service is not delivered in time or rejected by officer Metropolitan commissioner, BMRDA
Maximum number of days to wait to get the decision of the Competent Officer 15 Working Days
Whom to approach as 2nd appeal (Appellate Authority), if the decision of the Competent officer is not acceptable or not implemented? Additional Chief Secretary, Urban Development Department
Maximum no. of days to wait to get the decision of Appellate Authority 15 Working Days


Work Flow

Step

Description

No. of Days

Designation

1

Inward of proposal

1.00

Inward clerk

2

Technical scrutiny

10.00

Town planner

3

Verification of technical scrutiny of proposal

4.00

Assistant director of town and country planning

4

Review of technical scrutiny of proposal

3.00

Deputy director of town and country planning

5

Review and recommendation of proposal

3.00

Joint director of town and country planning

6

Verification of technical scrutiny of proposal

3.00

Additional director of town and country planning

7

Technical opinion for due consideration or calling for further information or documents from UDA or pa

3.00

Metropolitan planner and director

8

Recommending the proposal for consideration of government or calling for further information or documents from UDA or PA

3.00

Metropolitan commissioner

How would you rate the answer?


Excellent Good Neutral Poor Bad

Thank you for your response..


tesz.in
Hey , can you help?
Answer this question

Guide

Karnataka Voter List 2024 - Search By Name, Download

Empowering citizens to exercise their democratic rights is crucial, especially in the vibrant state of Karnataka. This concise guide offers clear steps for downloading the voter list, searc..
  Click here to get a detailed guide