Procedure involved to get this service:

•The owner who desires to change the name in BWSSB water/ sanitary connections due to transfer in ownership of the property, have to submit the application through online duly providing the details of the communication Address, location address, Khatha Number, PID Number, BWSSB RRNumber and Name of the consumer to be changed against the BWSSB connection.

•Sakala timeline starts from the time of submission of application online. GSC code will be generated and the application will be processed within 10 working days.

•AEE verifies the reports submitted by AE/WI and Revenue Manager /Draughts Man and approves the application for change of name.

•Demand note of Rs.250/- will be generated and Sakala timeline ends here.

•Consumer has to pay the amount of Rs.250/- through Online. On receipt of payment against demand note ownership of the BWSSB connections will be changed.

Fee/Charges to be paid to get the service:250/-

Maximum number of days to wait to get this service delivered:10 Working Days

Whom to approach as a appeal (Competent Officer), if the service is not delivered in time or rejected by officer: Executive Engineer

Maximum number of days to wait to get the decision of the Competent Officer:15 Working Days

Whom to approach as 2nd appeal (Appellate Authority), if the decision of the Competent officer is not acceptable or not implemented?:Additional Chief Engineer

Maximum no. of days to wait to get the decision of Appellate Authority:15 Working Days

Other information: www.bwssb.gov.in

Website (if online): www.bwssb.gov.in

Work Flow

Step Description No. of Days Designation
1 THE APPLICATION TO BE MOVED FROM ASSISTANT EXECUTIVE ENGINEER TO ASSISTANT ENGINEER FOR INSPECTION 2.00 Officer(General)
2 AFTER RECEIVING APPLICATION INSPECTION OF LOCATION TO BE CARRIED AND THE REPORT TO BE UPLOADED BY THE ASSISTANT ENGINEER. 3.00 Officer(General)
3 VERIFICATION OF THE DOCUMENTS BY REVENUE MANAGER/DRAUGHTSMAN AND REPORT TO BE UPLOADED. 2.00 Supervisor
4 ON VERIFICATION ASSISTANT EXECUTIVE ENGINEER PROVIDES APPROVAL FOR CHANGE OF OWNERSHIP OF BWSSB WATER/ SANITARY CONNECTION 3.00 Officer(General)

How would you rate the answer?


Excellent Good Neutral Poor Bad

Thank you for your response..


tesz.in
Hey , can you help?
Answer this question

Guide

Karnataka Voter List 2024 - Search By Name, Download

Empowering citizens to exercise their democratic rights is crucial, especially in the vibrant state of Karnataka. This concise guide offers clear steps for downloading the voter list, searc..
  Click here to get a detailed guide