Kerala Voter List 2024 - Search By Name, Download
Empowering citizens to exercise their democratic rights is crucial, especially in the vibrant state of Kerala. This concise guide offers clear steps for downloading the voter list, searchin..  Click here to get a detailed guide
KSFE
Sponsored
เดเต.เดเดธเต.เดเดซเต.เด เดญเดตเดจ เดตเดพเดฏเตเดช
30 เดตเตผเดทเด เดตเดฐเตเดฏเตเดณเตเดณ เดคเดฟเดฐเดฟเดเตเดเดเดตเต เดเดพเดฒเดพเดตเดงเดฟเดฏเดฟเดฒเตโ.. เดฒเดณเดฟเดคเดฎเดพเดฏ เดจเดเดชเดเดฟเดเตเดฐเดฎเดเตเดเดณเดฟเดฒเตเดเต เดจเตเดเดพเด 1 เดเตเดเดฟ เดฐเตเดช เดตเดฐเต เดตเดพเดฏเตเดช...T&C Apply
30 เดตเตผเดทเด เดตเดฐเตเดฏเตเดณเตเดณ เดคเดฟเดฐเดฟเดเตเดเดเดตเต เดเดพเดฒเดพเดตเดงเดฟเดฏเดฟเดฒเตโ.. เดฒเดณเดฟเดคเดฎเดพเดฏ เดจเดเดชเดเดฟเดเตเดฐเดฎเดเตเดเดณเดฟเดฒเตเดเต เดจเตเดเดพเด 1 เดเตเดเดฟ เดฐเตเดช เดตเดฐเต เดตเดพเดฏเตเดช...T&C Apply
Related Questions
-
Nandakumar N
Assistant Engineer, Soura Project, KSEB . Answered on March 05,2020Suppose I have set up a plant with a 40% subsidy scheme with 3 kWp capacity as part of the KSEB Soura scheme. If I have excess electricity after my consumption, can this be adjusted against my bill via net metering?
In model 2, every year amount will be adjusted on September 30. If there is an export of electricity, ...
1 82 1596 -
Nandakumar N
Assistant Engineer, Soura Project, KSEB . Answered on March 05,2020What will be the cost of Solar power plant with 3 kW capacity, if applied on a 40% scheme as part of the KSEB Soura scheme?
It will cost you Rs 1,62,000. If you opt for Model 2, you get 40% of it as the subsidy.So you need to pay ...
1 88 1416 -
KSFE
Sponsoredเดเต.เดเดธเตโ.เดเดซเต.เด เดจเตเดเตเดเด เดจเดฟเดเตเดทเตเดช เดชเดฆเตเดงเดคเดฟ
เดเต.เดเดธเตโ.เดเดซเต.เด เดฏเดฟเดฒเต เดจเดฟเดเตเดทเตเดชเดเตเดเตพเดเตเดเต เดเดจเดฟ เดเตเดเตเดคเตฝ เดจเตเดเตเดเด!
-
Nandakumar N
Assistant Engineer, Soura Project, KSEB . Answered on March 05,2020In the KSEB Soura scheme, does the electricity generated is taken to the grid or do we need to have battery to store the power?
In Off-Grid, you have the need for a battery. But KSEB's projects are On-Grid and in it, there is no ...
1 42 781 -
Nandakumar N
Assistant Engineer, Soura Project, KSEB . Answered on March 05,2020How much will be the cost for 2 kWp installation for KSEB Soura scheme?
As per the Ministry of New and Renewable Energy (MNRE) issued guidelines, the maximum amount the empanelled service providers ...
1 29 599 -
Nandakumar N
Assistant Engineer, Soura Project, KSEB . Answered on March 05,2020Will KSEB provides money to excess electricity in Model 2 of Soura scheme?
Yes, KSEB will provide money to excess electricity in Model 2 by the month of September every year.
1 12 194 -
KSFE
Sponsoredเดเต.เดเดธเตโ.เดเดซเต.เด เดจเตเดเตเดเด เดชเตเดฒเดธเต เดจเดฟเดเตเดทเตเดช เดชเดฆเตเดงเดคเดฟ
เดเต.เดเดธเตโ.เดเดซเต.เด เดฏเดฟเดฒเต เดจเดฟเดเตเดทเตเดชเดเตเดเตพเดเตเดเต เดเดจเดฟ เดเตเดเตเดคเตฝ เดจเตเดเตเดเด!
-
Nandakumar N
Assistant Engineer, Soura Project, KSEB . Answered on March 08,2020Is it possible for the customer to select the unit and company for solar panel installation in model 2 of the KSEB Soura scheme?
Customers can choose the company for solar panel installation in model 2 of the KSEB Soura scheme.
1 10 111 -
Nandakumar N
Assistant Engineer, Soura Project, KSEB . Answered on March 22,2020Will there be any restrictions if we have to sell the house within 25 years after taking the KSEB Soura scheme?
There are no restrictions as such for the house owner.
1 4 65 -
Nandakumar N
Assistant Engineer, Soura Project, KSEB . Answered on March 22,2020Is it true that once the KSEB soura plant was installed, the homeowner would not be allowed to do anything (like painting) for 25 years?
There are no restrictions as such for the house owner.
1 7 82 -
KSFE
SponsoredKSFE เดเดพเดฒเดเตเดธเดฟ เดเดฟเดเตเดเดฟเดเตพ
เดธเตเดธเตเดฅเดฟเดฐเดฎเดพเดฏ เดธเดฎเตเดชเดพเดฆเตเดฏเด, เดตเดพเดจเตเดณเดฎเตเดฏเดฐเตเดจเตเดจ เดธเดฎเตเดฆเตเดงเดฟ!!! 2024 April 1 เดฎเตเดคเดฒเตโ 2025 February 28 เดตเดฐเต
-
Kerala State Electricity Board
Government of Kerala . Answered on May 25,2020Is KSEB Soura subsidy available for all brands of solar panel installation?
The Soura project will be implemented through different agencies, who are shortlisted through a tendering process. The consumer will ...
1 0 618 -
Kerala State Electricity Board
Government of Kerala . Answered on July 08,2020Does the KSEB Soura project have any meter or any device to know the consumption, produced electricity, electricity taken by KSEB etc. ?
There will be net meter connected at the premises of the consumer.
1 5 285 -
Kerala State Electricity Board
Government of Kerala . Answered on July 08,2020Does the KSEB Soura scheme require any additional wiring or alteration?
Additional wiring, if required by the consumer, shall be borne by the consumer. Normally, additional wiring is not required
1 0 89 -
Kerala State Electricity Board
Government of Kerala . Answered on July 28,2020Who will have ownership of solar panels in both Soura models? I mean, solar panel property ownership. In case of house ownership get changed (due to sale or partitions etc), Is there permission required from KSEB?
Model 2: Consumer has full ownership. He/she can sell the property, with or without solar panels Model 1: The conditions ...
2 0 110 -
Kerala State Electricity Board
Government of Kerala . Answered on September 09,2020I have applied for KSEB Soura Scheme through web portal. Now it shows "processed" against my consumer number. How do I know the status of the application. What are the next steps to be taken by me?
Next step is site inspection. That will happen in next two months. Currently, you cannot check the status of ...
1 0 2386 -
Try to help us answer..
-
I'm planning to upgrade my ongrid rooftop solar from 3 kw to 5 kw as part of KSEB Soura scheme. Will I have to buy a new 5 kw dc ac inverter. Or Can I buy a new 2 kw inverter and install this inverter additionally Or Will I need to buy a new 5kw inverter
Write Answer
-
I have installed KSEB solar power plant in my house. Suppose the plant made 400 units and I have used 500 units a month. So should I pay the electricity bill for 100 units or will it be adjusted from the previous month's excess unit reserve?
Write Answer
-
How much time it would take in Kerala for getting metre changed by KSEB for on grid Solar connection after submitting papers after installation?
Write Answer
-
Kerala State Electricity Board-Soura (Solar project)-Subsidy scheme 1C with an agreement that excess unit produced from the rooftop would be taken by KSEB through on-grid system and will be paid back. But more than an year passed no payment received. What to do?
Write Answer
-
Can one convert an KSEB Soura on-grid system to offgrid at a later date?
Write Answer
-
I'm planning to upgrade my ongrid rooftop solar from 3 kw to 5 kw as part of KSEB Soura scheme. Will I have to buy a new 5 kw dc ac inverter. Or Can I buy a new 2 kw inverter and install this inverter additionally Or Will I need to buy a new 5kw inverter
-
Trending Questions
-
JOY MRC
Answered on September 19,2021How to convert license number 5/9308/2014 from Kerala to this new format in Digilocker?
Use mparivahan app for RC and License addition which is equivalent to digilocker and also valid for Rto checking. ...
2 2844 59449 -
Subhash Chandran
Retired Dy Tahsildar and Land Consultant, Mobile- 8848753166 . Answered on September 07,2023เดธเตเดฅเดฟเดฐเดชเตเดเตเด เดเดจเตเดจเดพเตฝ เดเดจเตเดคเดพเดฃเต?
Settlement เดเดพเดฒเดคเตเดคเต เดฎเดฒเดฌเดพเตผ เดชเตเดฐเดฆเตเดถเดคเตเดคเตเดณเตเดณ เดญเตเดฎเดฟเดเดณเต เดจเดเตเด, เดคเตเดชเต, เดธเตเดฅเดฟเดฐเด เดชเตเดเตเด,เด เดธเตเดฅเดฟเดฐเดค เดชเตเดเตเด, เดจเดฟเดเตเดคเดฟเดเตเดเตเดเดพเดคเดคเต, เดชเตเดฑเดฎเตเดชเตเดเตเดเต เดเดจเตเดจเดฟเดเตเดเดจเต เดเดฑเดพเดฏเดฟ เดคเดฟเดฐเดฟเดเตเดเดฟเดฐเตเดจเตเดจเต…เดธเตเดฅเดฟเดฐเดชเตเดเตเด เดเดจเตเดจเดพเตฝ เดเดฒเตเดฒเดพ เดตเตผเดทเดตเตเด เดธเตเดฅเดฟเดฐเดฎเดพเดฏเดฟ ...
1 0 2503 -
Niyas Maskan
Village Officer, Kerala . Answered on January 26,2021How to get the affidavit for caste certificate in Kerala ?
เดเดฐเต เดตเตเดณเตเดณ เดชเตเดชเตเดชเดฑเดฟเตฝ เดฎเตเดเดณเดฟเตฝ เด เดซเดฟเดกเดตเดฟเดฑเตเดฑเต เดเดจเตเดจเต เดฐเตเดเดชเตเดชเตเดเตเดคเตเดคเตเด เด เดคเดฟเดจเต เดคเดพเดดเต เดเตผเดเตเดเดพเดฃเต เด เดคเต เดธเดฎเตผเดชเดฟเดเตเดจเดคเต เด เดคเต เดฐเตเดเดชเตเดชเตเดเตเดคเตเดคเตเด. เด เดคเดฟเดจเต เดถเตเดทเด เดเดฐเดพเดฃเต เดธเดฎเตผเดชเดฟเดเตเดจเดคเต เด เดตเดฐเตเดเต เดตเดฟเดตเดฐเด เดจเตฝเดเตเด. เด เดคเดฟเดจเต ...
1 378 19517 -
Niyas Maskan
Village Officer, Kerala . Answered on August 31,2023What is the format affidavit for non creamy layer certificate in Kerala?
เด เดซเดฟเดกเดตเดฟเดฑเตเดฑเต เดเดจเตเดจ เดตเดฟเดฒเตเดฒเดเต เดเดซเตเดธเตผ เดฎเตเตปเดชเดพเดเต เดเดจเตเดจ เดตเดฟเดฒเตเดฒเตเดเดฟเตฝ เดเดจเตเดจ เดตเดพเตผเดกเดฟเตฝ เดเดจเตเดจ เดตเตเดเตเดเดฟเตฝ เดคเดพเดฎเดธเดฟเดเตเดเตเดจเตเดจ เดเดจเตเดจเดฏเดพเดณเตเดเต เดฎเดเตป เดเดฏ เดเดพเตป เดฌเตเดงเดฟเดชเตเดชเดฟเดเตเดเตเดจเตเดจ เดธเดคเตเดฏเดตเดพเดเตเดฎเตเดฒเด เดเดพเตป เดฎเตเตฝเดเดพเดฃเตเดจเตเดจ เด เดกเตเดฐเดธเดฟเตฝ เดเดคเตเดฐ ...
1 171 3536 -
James Joseph Adhikarathil
Former Deputy Collector, Alappuzha,Leading Land Consultant in Kerala. Call 9447464502 . Answered on April 14,2023Where are the AI Camera locations of motor vehicle department in Kerala?
*All Kerala MVD AI camera locations* Thiruvananthapuram Parassala Thiruvananthapuram Pambukala Thiruvananthapuram Kovalam Jn Thiruvananthapuram Neyyattinkara_2 Thiruvananthapuram Neyyattinkara_1 Thiruvananthapuram Thozhukkal Thiruvananthapuram Balaramapuram_1 Thiruvananthapuram Balaramapuram_2 Thiruvananthapuram Pallichal Jn Thiruvananthapuram Thiruvallom Thiruvananthapuram Kumarichantha Thiruvananthapuram ...
1 0 79224 -
James Joseph Adhikarathil
Former Deputy Collector, Alappuzha,Leading Land Consultant in Kerala. Call 9447464502 . Answered on March 19,2023I had applied to convert my wet land to dry land in Kerala 2 months back. How could i check the application status online? If i try with revenue dep. website they ask the application no. Where can i get application no? I have only one receipt.
Application number is available in the receipt. Also open the site if you know the user id and pass ...
1 146 4997 -
James Joseph Adhikarathil
Former Deputy Collector, Alappuzha,Leading Land Consultant in Kerala. Call 9447464502 . Answered on April 14,2023เดเดจเตเดคเดพเดฃเต เดตเดฟเดฒเตเดฒเตเดเต เดเดซเตเดธเดฟเดฒเต BTR เด เดฅเดตเดพ เดฌเตเดธเดฟเดเต เดเดพเดเตเดธเต เดฐเดเดฟเดธเตเดฑเตเดฑเตผ . เดชเตเดฐเดพเดงเดพเดจเตเดฏเดฎเตเดจเตเดคเต?
เดเดฐเต เดตเดฟเดฒเตเดฒเตเดเดฟเดฒเตเดณเตเดณ เดเดฒเตเดฒเดพ เดญเตเดฎเดฟเดเดณเตเดเตเดฏเตเด เดธเตผเดเตเดเดพเตผ เดญเตเดฎเดฟเดฏเดพเดฏเดพเดฒเตเด เดชเตเดฑเดฎเตเดชเตเดเตเดเต เดญเตเดฎเดฟ เดเดฏเดพเดฒเตเด เดธเตผเดตเตเดตเต เดจเดฎเตเดชเตผ เดเตเดฐเดฎเดคเตเดคเดฟเดฒเตเดณเตเดณ เดตเดฟเดตเดฐเดเตเดเตพ เดเดพเดฃเดฟเดเตเดเตเดจเตเดจ เดธเตเดฅเดฟเดฐเด เดฐเดเดฟเดธเตเดฑเตเดฑเตผ เดเดฃเต เด เดเดฟเดธเตเดฅเดพเดจ เดญเตเดฎเดฟ ...
1 250 4991 -
Gopakumaran Nair S
Junior Superintendent, Animal Husbandry Department. Taking spark related classes for government employees since 2009 . Answered on April 23,2024เดเดฐเต เดเตเดตเดจเดเตเดเดพเดฐเดจเตเดฑเต 2002 เดฎเตเดคเดฒเตเดณเตเดณ FBS เดตเดฟเดตเดฐเดเตเดเตพ เดฒเดญเตเดฏเดฎเดพเดเดพเดจเตเดจเตเดคเดพเดฃเต เดตเดดเดฟ?(PBR เดฒเดญเตเดฏเดฎเดฒเตเดฒ) เดเดตเดฟเดเต เด เดจเตเดตเตเดทเดฟเดเตเดเดพเตฝ เดฒเดญเตเดฏเดฎเดพเดเตเด?
เดชเดดเดฏ เดฌเดฟเดฒเตเดฒเต เดเตเดชเตเดชเดฟ เดฏเดฟเตฝ เดเดฟเดเตเดเตเด
1 0 22 -
Venu Mohan
Citizen Volunteer, Kerala . Answered on January 01,2022Which are the medisep hospitals in Kozhikode ?
Following are the list of MEDISEP hospitals in Kozhikode. Hospital Name Specialization EMS Memorial Co- operative Hospital &Research centre - 2708D General Medicine, ...
1 321 9151 -
KSFE
Government of Kerala . Answered on January 15,2021What is the procedure if I can't continue the KSFE Chitty?
If you can’t continue the KSFE Chitty please intimate the matter in the KSFE branch in which you enrolled ...